Tuesday, December 28, 2010

LOCKED!

Our FIXED interest rate is 4.75%. :-)

Now we wait for approval of the loan.

Oy!

Windows and such!

So, pre-drywall meeting is scheduled for MONDAY (Jan. 3) with drywall to begin on Wednesday (holy craaaaaaaaaaaap!). :)

Our mortgage rep locked the rate already, too! Yikes! It's getting more and more real...


















  



Saturday, December 25, 2010

Small changes...

So, we visited the homesite today, and saw that a front door had been installed, and the exterior outlets have been finished. I am sure there has been some other work, but it was probably not much to see unless we knew where to look.

Monday I meet with the supervisor to discuss the placement of a light in the dining area.

Wednesday, December 22, 2010

Electrical & plumbing! Tar paper on the roof!

Pipes in the front lawn.

Back of the house with tar paper and shingles on the roof.

Back of the house with tar paper and shingles on the roof.

Side of the house with tar paper and shingles on the roof.

Side of the house with tar paper and shingles on the roof.

Closer view of the house with roof almost done.

Front of the house, tar paper and shingles on roof.

More duct work in the ceiling.

Air system in garage.

Water heater hook up!

Master bath shower enclosure.

Duct work in the ceiling.

Back of air system in garage.

Guest bathroom tub enclosure.

Washer and dryer hook ups.

Conduit where wiring goes into fuse box.

Garage. Air handler in the middle. Fuse box on the right hand wall.